Honesdale Borough expects numerous road construction projects to get underway in the coming weeks and months.
The following is the information available to the borough. All dates and timelines are subject to change. The borough seeks to keep the public aware of scheduled work that may impact their daily lives.

Please contact contractors if you have questions about scheduled roadwork. Borough staff does not always have specific information regarding projects. Also, timeframes (duration, dates) do not reflect the actual length of time the construction will take to complete.
| STREET LOCATION | TYPE OF WORK & LENGTH | START DATES | DURATION | CONTRACTOR & TELEPHONE | UTILITY |
| 4th Street | REMOVE GUIDERAIL | 5/1-5/12 | 21 Days | MINICHI INC 570-954-625 | DOT |
| Terrace Heights | SANITARY SEWER MAIN AND LATERAL REPLACEMENT | 5/7-5/18 | 1 Week | PACT CONSTRUCTION INC 610-960-1715 | CWRA |
| Grove Street | SANITARY SEWER LATERAL INSTALLATIONS | 5/18-5/28 | 1 Month | PACT CONSTRUCTION INC 610-960-1715 | CWRA |
| Grove Street | SANITARY SEWER REPLACEMENT | 5/21-5/28 | 1 Month | PACT CONSTRUCTION INC 610-960-1715 | CWRA |